Get premium membership and access revision papers with marking schemes, video lessons and live classes.
  OR
Processing. Please wait.

 Form 4 Mathematics Paper 1 Exam Revision Questions With Answers Set 2

Twenty four men working at the rate of 10 hours a day take 18 days to complete a certain job. How long would 30 men working 9 hours a day take to complete the same job?

 (2m 22s)
455 Views     SHARE

|